Technology appraisals and highly specialised technologies charging timeline
A timeline showing where in the evaluation process companies will be charged.
Timeline
13 to 4 months before ITP
Change fee and refunds: not applicable.
Topic selection (-13 months)
Company update UK Pharmascan with regulatory plans.
Check regulatory plans with company (-9 months)
Confirm timelines and topic scheduled
Request URN (-6 months)
URN received
Invoice issued
5 months before ITP.
NICE payment terms, 30 days from invoice.
0 to 4 months before ITP
Change fee: applicable.
Scope consultation begins
(-2 months)
Only if URN has been provided.
Scope consultation ends
(-1 month)
0 to 7 months after ITP
Change fee: not applicable.
Refunds: applicable.
Invitation to participate issued (0 months)
Submissions due (+2 months)
External Assessment Report (+4 months)
Technical engagement.
7 to 9.5 months after ITP
Change fee: not applicable
Refunds: applicable.
Committee preparation
1st committee meeting incuding draft guidance (+7 months)
Final draft guidance (+ 8 months)
2nd committee meeting.